News Centre

What are the specifications and models of low-temperature evaporators? How to choose the processing capacity?

Date:2026-11-18 Hits:0

1、 Conventional standard specification division

Low temperature evaporators are generally classified based on their rated evaporation capacity (standard operating conditions), with the mainstream being the integrated pry and install model, which is divided into four gears and can support non-standard customization:


Small scale testing/laboratory, small production line models: 300L/D, 500L/D (0.3T, 0.5T per day) suitable for laboratory waste liquid, small amount of cleaning wastewater, sample verification, and reduction of machining single point cutting fluid waste liquid. It occupies a small area and can operate intermittently.


Small industrial standard models: 1T/D, 2T/D, 3T/D, 5T/D are the main models with the largest market usage. This range is mostly used for electroplating, machining, surface treatment, emulsion, and RO concentrated water reduction. It is fully automatic and can be monitored by a single person.


Medium to large industrial models: 6T/D, 8T/D, 10T/D, 15T/D, 20T/D production line wastewater continuous output, multi process waste liquid centralized collection scene, can operate continuously, with more complete self-control support.


Large water capacity scheme: For quantities above 20T/D, multiple units are generally connected in parallel, without blindly producing oversized units, which facilitates phased production and maintenance without stopping production.


Additional explanation: The nominal evaporation capacity of the model is the evaporation capacity under standard water quality, standard vacuum, and rated temperature; Under conditions of complex water quality, high viscosity, high oil content, and high salt saturation, the actual evaporation rate will decrease. According to the heating source, it can be divided into heat pump type low-temperature evaporator, hot water heating type, and electric heating vacuum low-temperature evaporator. Heat pump models have better energy consumption and are the mainstream choice; The materials available are 304, 316L, 2205 duplex steel, and titanium, matched according to chloride ions, acidity and alkalinity, and corrosive waste liquids.


2、 Correct selection method for processing capacity (emphasis)

Many customers directly choose models based on the daily average total amount of wastewater, making it easy to choose smaller ones. The selection follows this logic:


Firstly, confirm the daily waste liquid production and peak water volume, and prioritize the peak water volume during peak season as the benchmark, rather than the average water volume;


Confirm the daily operating time of the equipment: Most factories do not operate 24 hours a day, commonly 8 hours/12 hours/16 hours/20 hours. The total water volume should be allocated to the effective operating time and converted into hourly evaporation;


Reserve a margin of 10% to 20% to cope with water quality fluctuations, cleaning shutdowns, peak season increments, and avoid long-term full load and overload operations;


Adjust the load based on the characteristics of the waste liquid:


Oil containing, high COD, high viscosity, easily foaming waste liquid: high concentration resistance, it is recommended to increase the remaining amount;


Low salt, clean and concentrated water: stable load, according to the basic margin is sufficient;


The higher the target concentration ratio, the higher the unit evaporation load, and for the same tonnage, it needs to be increased by one level.


A simple example

The factory has a daily average of 4 tons of waste liquid, and only allows equipment to operate for 10 hours per day, with a peak of 4.5 tons per day. Converted hourly evaporation demand: 4500L ÷ 10h=450L/h, needs to be matched with models close to 5T/D instead of directly selecting 4T models.


3、 Matching conditions that need to be confirmed synchronously during selection

Waste liquid quality: TDS salt content COD、pH、 Chloride ions, oil content, suspended solids, and whether they are prone to crystallization and foaming;


Goal: Only reduce hazardous waste, reuse condensed water, or require salt crystallization;


Site conditions: power supply, cooling water, compressed air, site size, whether explosion-proof is required;


Operation mode: intermittent batch processing or 24-hour continuous feeding.


4、 One sentence summary of selection

The water quantity determines the model gear, the water quality determines the material and load margin, and the operating time determines the hourly evaporation index; It is recommended to conduct a small-scale water sample test for complex wastewater before finalizing the model.